1 Routine Maintenance and Capital Overhauling of Boiler Burner Panel, and CMR of Bowl mills XRP-763/803 of stage I & II at KSTSP KSTSP, RVUNL Running
2 Annual Maintenance Contract for Milling System for 3x500 MW Units at APCPL, Jhajjar APCPL, NTPC Running
3 Routine, Breakdown, Preventive Maintenance and Annual Overhauling works of Coal Mills & ID/FD/PA/Vapour Fans/Seal/ Scanner Air Fans of 2x110 MW (Unit-1&2) and 2X120MW (Unit-3&4) at GNDTP GNDTP, PSPCL Running
4 Routine, Breakdown, Preventive Maintenance and Annual Overhauling of Turbine, Generators and its Auxialiries, HP Bypass, LP Bypass, Regenrative System, Pipings and Valves etc. of 2x210 and 2x250 MW Units. GHTP, PSPCL Completed
5 HP & LP welding in Boiler & Turbine area and Steam tracing lines, Cleaning of Boiler drum, Boiler Furnance checking, Replacement of Bafffles/Buck stays, Erection, Operations and Maintenance of Sky Climber, Furnance cleaning & Measurement of Boiler tube thickness etc. KSTSP, RVUNL Completed
6 Routine & Preventive Breakdown and Maintenance and Annual Overalhauling of 2x210 and 2x250 MW BHEL make Boiler Pressure parts , Wind box & Burners, Ducts , Damper & Gates, Coal pipes, Air Pre-heaters, ESPs, Safety Valves, HP/LP Pipings and manual Valves, Fuel firing System etc. GHTP, PSPCL Completed
7 Annual Maintenance Contract of TG and its Aux. of 2x600 MW Units RGTPP, HPGCL Completed
8 Routine and Breakdown Maintenance of Turbine, Heat Exchangers and Their Componenets for 6x250MW Units. SSTPS, RVUNL Completed
9 Breakdown/ Preventive Maintenance of TG Equipments and Overhauling of Associated Auxiliaries of 6x210 MW 'KWU' design BHEL make TG units. GGSSTP,PSPCL Completed
10 Overhauling of Pressure Parts, Burners & HP valves of 250MW Boiler Unit #7 PTPS, HPGCL Completed
11 Annual Maintenanace Contrcat for General/Routine/Preventive Maintenance of Boiler and its Aux. of 2x600 MW Units RGTPP, HPGCL Completed
12 Routine, Breakdown, Preventive Maintenance and Annual Overhauling of 2x210 MW & 2x250MW Boiler Aux. such as ID/FD/PA & Seal air Fans, Bowl Mills, RC Feeders & Bunkers, Coal Valves , Mill reject Handling system, transportation/dumping of coal mill reject etc. GHTP, PSPCL Completed
13 Annual Rate Contrcat for Mechanical Maintenance jobs in Steam Generation Plant & CHP at NFL, Bathinda NFL, Bathinda Completed
14 Replacement of Waste Heat Boiler AEC101 Complete Assembly and welding of Lip Seal with Sub Reactor Main Flange at NFL, Bathinda NFL, Bathinda Completed
15 Annual Maintenance Contract for Milling System for 3x500 MW Units at APCPL, Jhajjar APCPL, NTPC Completed
16 Annual Maintenance Contract of Coal Mills (Bowl mill HP 1103) and Gravimetric RC feeders (Belt type) for 2x600 Units RGTPP, HPGCL Completed
17 Routine , Breakdown & Capital Maintenance of Ball Tube Mill, Seal Sir System, Air Ducts, Furnace Burner Panel, PF Piping etc. of 2x250 MW Unit 1 & 6 at SSTPS SSTSPS, RVUNL Completed
18 Overhauling of Coal Burners,Wind Box,& HP Valves of 1x600MW RGTPP, HPGCL Completed
19 Routine, Breakdown & Capital Maintenanace of Burner Panel & PF Piping of Unit 1 to 6 (2x250MW) at SSTPS. SSTSPS, RVUNL Completed
20 Rountine, Breakdown & Capital Maintenance of Air Pre-Heaters of Unit 1 to 6 of 250MW each. SSTSPS, RVUNL Completed
21 Rountine,Breakdown & Capital Maintenance of ID/FD/PA Fans of Unit 1 to 6 of 250MW each. SSTPS, RVUNL Completed
22 Capital, Routine, Breakdown Maintenance of Air Pre-Heaters of Unit 1 to 7 at KSTSP,Kota KSTPS,RVUNL Completed
23 Annual Overhauling of Boiler Pressue Parts & Air pre-heaters and its Auxiliaries of 2x210 BHEL make units 5 & 3 GGSSTP,PSPCL Completed
24 Routine, Breakdown & Preventive Mtc. and Overhauling Jobs of various Mech. Aux. comprising of Air Compressors, Vertical & Horizontal Pumps, DM Plant, Fire Fighting System, Hydrogen Gas Plant, LP Piping & Valves, O&M of Mechanical Workshop and Plant drainage Pumps of 2x210 and 2x250MW units GHTP, PSPCL Completed
25 Overhauling of Sulphuric Acid Plant at Abhishek Industries, Barnala Trident Group Completed
26 Breakdown/Prventive Maintenance & Overhauling of DM plants,DG Sets, Compressors and other allied Mechanical Auxiliaries of 6x210 MW Units . GGSSTP,PSPCL Completed
27 Overhauling of ESP, Ducts & dampers at Abhishek Industries, Barnala Trident Group Completed
28 Replacement of Economizer Coils of Thermax Make Boiler at KPM KPM, Amritsar Completed
29 Assistance in commisioning of 2x600 MW Power Plant at RGTPP, Hisar RUEPL, Reliance Completed
30 Replacement of Air Pre Heaters (Tubular Type) of Boiler at KPM. KPM, Amritsar Completed
31 Dismantling, Erection , Commissioning & Hard Facing work of Vapour Fans for 1x120 MW Unit at GNDTP ALSTOM Completed
32 Replacement of Girth Gear of Ball tube Mill of Unit-2 (250MW) at SSTPS. SSTPS, RVUNL Completed
33 Work of attending Hydrogen Gas Leakage of Genertor of 110MW Unit#2 at GNDTP. GNDTP, PSPCL Completed
34 Overhauling of Boiler Pressure Parts, Wind Box, PC Line, Safety Valves, APH,ESP, Ducts & Dampers of Unit#1 at GNDTP. GNDTP, PSPCL Completed
35 Routine, Breakdown, Preventive Maintenance & Overhaul Jobs(Mech. Works) of Turbine, Generator & its Auxiliaries HP Bypass, LP Bypass, Regenerative System, Piping & Valves etc. of 2x210 MW & 2x250 MW Units of GHTP, Stage I & II . GHTP , PSPCL Running


About Us

We at GILL ENGINEERING PVT.LTD are fully geared up to provide expertise engineering services to our esteemed clients across a wide array of domains. Our spectrum of business activities covers the following: Boiler & its AuxiliariesTurbine & its AuxiliariesCoal Mills & FansCompressors & PumpsCrushers, Rotary Breakers & Conveyor  System Wagon Tipplers and Stacker & ReclaimersFabrication & Erection of Piping & StructureConveyor Belt JointingCeramic & Rubber Lagging of Pulleys O&M of Ash Handling PlantO&M of Hydrogen Plants

Find us at

REGD. OFFICE:
#1, Vishvas Nagar, Goniana Road, P.O. NFL, Bathinda-151003

0164-2270895, 3297051
gill.engineering@yahoo.in

Send us a message

X